Is there way to extract week of quarter from a date column?

Siddhesh_Bandekar
Member
The default week() function extracts the week number from the start of the year and runs 1 to 53 or 54. I need to show week number within the quarter, running 1 to 13 or 14 within each qtr.
Is there a way to do this using beast mode or using the formula tile in Magic ETL ?
Thanks!
Tagged:
0
Best Answer
-
Hi @Siddhesh_Bandekar you could try a beast mode like this, assuming the first 3 quarters have 13 weeks and Q4 takes the overflow:
CASE when WEEK(`Date`) >= 39 then WEEK(`Date`) - 38 else MOD(WEEK(`Date`),13) + 1 END
2
Answers
-
Hi @Siddhesh_Bandekar you could try a beast mode like this, assuming the first 3 quarters have 13 weeks and Q4 takes the overflow:
CASE when WEEK(`Date`) >= 39 then WEEK(`Date`) - 38 else MOD(WEEK(`Date`),13) + 1 END
2 -
Thanks @MichelleH. This is what I was looking for.
0
Categories
- All Categories
- Product Ideas
- 2.1K Ideas Exchange
- Connect
- 1.3K Connectors
- 309 Workbench
- 7 Cloud Amplifier
- 10 Federated
- Transform
- 663 Datasets
- 119 SQL DataFlows
- 2.3K Magic ETL
- 823 Beast Mode
- Visualize
- 2.6K Charting
- 86 App Studio
- 46 Variables
- Automate
- 193 Apps
- 483 APIs & Domo Developer
- 87 Workflows
- 23 Code Engine
- AI and Machine Learning
- 23 AI Chat
- 4 AI Projects and Models
- 18 Jupyter Workspaces
- Distribute
- 117 Domo Everywhere
- 283 Scheduled Reports
- 11 Software Integrations
- Manage
- 143 Governance & Security
- 11 Domo Community Gallery
- 49 Product Releases
- 13 Domo University
- Community Forums
- 41 Getting Started
- 31 Community Member Introductions
- 116 Community Announcements
- 5K Archive