Does running an ETL with a schedule change the future run times?

If I have a flow that is scheduled to run every two hours, and I do a manual run between those times, will the next run happen two hours from then or continue on the original schedule?

Best Answer

  • MichelleH
    MichelleH Coach
    Answer ✓

    @DataLyd The dataflow will continue to run on the original schedule even if you manually run it.