How to calculate % of projects assigned?

Hi there. I'm trying to setup a beast mode calculation but not sure the best approach for it.

I have a column that shows the number of days it takes for a new project to get assigned for example if opened on 19 Sep, assigned on 22 Sep - it would show up as 3 days.

I'm looking to do a quality check to see what percentage % of projects have been assigned within 10 business days. What would be the best way to go about doing this?

Best Answer

  • RobSomers
    RobSomers Coach
    Answer ✓

    @domodonuts

    SUM(case when 'DaysToAssigned' <= 10 then 1 else 0 end)/SUM(1)

    **Was this post helpful? Click Agree or Like below**

    **Did this solve your problem? Accept it as a solution!**

Answers

  • RobSomers
    RobSomers Coach
    Answer ✓

    @domodonuts

    SUM(case when 'DaysToAssigned' <= 10 then 1 else 0 end)/SUM(1)

    **Was this post helpful? Click Agree or Like below**

    **Did this solve your problem? Accept it as a solution!**

  • Thanks Rob - appreciate the help 😊